Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
您可能感興趣的試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A.confused
B.same
C.overlap
D.dissever
() from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
A.Process
B.Milestone
C.Work
D.Deliverables
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
A.Metrics
B.Measurement
C.Benchmarking
D.Baseline
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
最新試題
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
空白(5)處填()
The connection between two networks from an intemet is handled by a machine known as a()
空白(1)處填()
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
An example of scope verification is ().
空白(3)處填()
空白(2)處填()
Contract closeout is a process that involves()
空白(1)處填()