單項(xiàng)選擇題

Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

A.qualityplanning
B.qualityassurance
C.qualityperformance
D.quality control


你可能感興趣的試題

4.單項(xiàng)選擇題

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Riskldentification
B.Quantitative RiskAnalysis
C.Qualitative RiskAnalysis
D.Risk Monitoring and Control

最新試題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

題型:?jiǎn)雾?xiàng)選擇題

空白(1)處填()

題型:?jiǎn)雾?xiàng)選擇題

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

題型:?jiǎn)雾?xiàng)選擇題

空白(3)處填()

題型:?jiǎn)雾?xiàng)選擇題

空白(3)處填()

題型:?jiǎn)雾?xiàng)選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

題型:?jiǎn)雾?xiàng)選擇題

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

題型:?jiǎn)雾?xiàng)選擇題

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

題型:?jiǎn)雾?xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

題型:?jiǎn)雾?xiàng)選擇題

空白(2)處填()

題型:?jiǎn)雾?xiàng)選擇題