A.Use Capacity on Demand to add the resources.
B.Use DLPAR to add the resources and select the 'permanent' option.
C.Use DLPAR to add the resources, and change the partition profile.
D.Use an Operating System command to permanently request the resources.
您可能感興趣的試卷
你可能感興趣的試題
A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.
What is the minimum PowerVM Edition which provides this feature?()
A.Basic
B.Express
C.Standard
D.Enterprise
A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window.
Which solution addresses this problem without requiring additional hardware?()
A.AddingVMControl will automate processor resource allocation during peak workloads.
B.Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors.
C.Add processing resources during the times they are required using Utility Capacity on Demand.
D.Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads.
A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention.
Which of the following meets the customer requirement?()
A.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped.
B.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped.
C.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day.
D.Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing.
A.8 desired processing units and 8 desired virtual processors
B.2 desired processing units and 8 desired virtual processors
C.8 desired processing units and 32 desired virtual processors
D.2 desired processing units and 32 desired virtual processors
A.PCIe adapters
B.PCI-X adapters
C.PCI-X andPCIe adapters
D.PCI, PCI-X andPCIe adapters
最新試題
A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()
A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.Which action will reduce the potential vendor software costs?()
While using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?()
A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()
A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window.Which solution addresses this problem without requiring additional hardware?()
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.Which system software solution component supports the customer requirement?()
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()
Which system provides the highest performance per core, and the least cost for applications licensed per core?()
Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()