單項(xiàng)選擇題

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.

A.proceedings
B.controls
C.forecastings
D.Prelibations


你可能感興趣的試題

2.單項(xiàng)選擇題

()involves using mathematical techniques to forecast future outcomes based onhistorical results.

A.Trendanalysis
B.Qualityaudit
C.Defect repair review
D.Flowcharting

最新試題

空白(2)處填()

題型:單項(xiàng)選擇題

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

題型:單項(xiàng)選擇題

空白(3)處填()

題型:單項(xiàng)選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

題型:單項(xiàng)選擇題

A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.

題型:單項(xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

題型:單項(xiàng)選擇題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

題型:單項(xiàng)選擇題

You are working on the cost budget for one project. Which of the following is true()

題型:單項(xiàng)選擇題

The connection between two networks from an intemet is handled by a machine known as a()

題型:單項(xiàng)選擇題

Contract closeout is a process that involves()

題型:單項(xiàng)選擇題