單項(xiàng)選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders


你可能感興趣的試題

1.單項(xiàng)選擇題

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

2.單項(xiàng)選擇題

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

3.單項(xiàng)選擇題

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

4.單項(xiàng)選擇題

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

5.單項(xiàng)選擇題

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新試題

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

題型:?jiǎn)雾?xiàng)選擇題

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

題型:?jiǎn)雾?xiàng)選擇題

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

題型:?jiǎn)雾?xiàng)選擇題

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

題型:?jiǎn)雾?xiàng)選擇題

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

題型:?jiǎn)雾?xiàng)選擇題

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

題型:?jiǎn)雾?xiàng)選擇題

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

題型:?jiǎn)雾?xiàng)選擇題

In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .

題型:?jiǎn)雾?xiàng)選擇題

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

題型:?jiǎn)雾?xiàng)選擇題

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.